# The Network Rail (Waverley Steps) Order 2010, Paragraph 6


(1) Not less than 28 days before commencing the construction of any work of the type referred to in paragraph 4(2) that is near to, or will or may affect, any apparatus the removal of which has not been required by Network Rail under paragraph 4(2), Network Rail shall submit to the specified undertaker a plan, section and description of the work to be constructed.
(2) Any such work shall be constructed only in accordance with the plan, section and description as submitted under sub-paragraph (1) and in accordance with such reasonable requirements as may be made by the specified undertaker in accordance with sub-paragraph (3) for the alteration or otherwise for the protection of the apparatus, or for securing access to the apparatus, and the specified undertaker shall be entitled by its officer to watch and inspect the construction of that work.
(3) Any requirements made by the specified undertaker under sub-paragraph (2) shall be made within a period of 14 days beginning with the date on which a plan, section and description under sub-paragraph (1) are submitted to it.
(4) If a specified undertaker, in accordance with sub-paragraph (3) and in consequence of the works proposed by Network Rail, reasonably requires the removal of any apparatus and gives notice to Network Rail of that requirement, the foregoing provisions of this Part of this Schedule shall have effect as if the removal of such apparatus had been required by the specified undertaker under paragraph 4(2).
(5) Nothing in this paragraph shall preclude Network Rail from submitting at any time, or from time to time, but in no case less than 28 days before commencing the construction of any work, a new plan, section and description of the work in lieu of the plan, section and description previously submitted, and at the time of such submission the provisions of this paragraph shall apply to, and in respect of, the new plan, section and description.
(6) Network Rail shall not be required to comply with sub-paragraphs (1) and (2) in a case of emergency but, in that case, it shall give notice to the specified undertaker as soon as is reasonably practicable, and shall provide a plan of the works so soon as reasonably practicable thereafter, and shall comply with those sub-paragraphs so far as is reasonably practicable in the circumstances.

---
Source: https://www.legislation.gov.uk/ssi/2010/188/schedule/8/paragraph/6 (the official version)
Page: https://openlegislation.uk/network-rail-waverley-steps-order-2010/schedule-8/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.