# The Network Rail (Werrington Grade Separation) Order 2018, Article 9: Power to execute street works


(1) Network Rail may, for the purposes of the authorised works, enter on any of the streets specified in Schedule 4 (streets subject to street works) as are within the Order limits and may—
(a) break up or open the street, or any sewer, drain or tunnel under it;
(b) place apparatus in the street;
(c) maintain apparatus in the street or change its position; and
(d) execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b) and (c).
(2) In this article “apparatus” has the same meaning as in Part 3 of the 1991 Act.

---
Source: https://www.legislation.gov.uk/uksi/2018/923/article/9 (the official version)
Page: https://openlegislation.uk/network-rail-werrington-grade-separation-order-2018/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.