# The Network Rail (Werrington Grade Separation) Order 2018, Schedule 2: ACQUISITION OF LAND FOR ANCILLARY WORKS


(1)
Area
(2)
Number of land shown on the deposited plans
(3)
Purposes for which land may be acquired
City of Peterborough
11, 15, 16, 24, 27, 31 to 34, 37, 40, 51, 51a, 52
Worksite and access for construction of the authorised works
Diversion of utility apparatus
18 to 23, 190, 191, 195, 214 to 220
Diversion of utility apparatus
58, 59, 76, 85
Worksite and access for construction and maintenance of the authorised works
62
Worksite and access for construction and maintenance of the authorised works
Diversion of utility apparatus
77 to 80, 105, 183, 189, 198, 209, 211
Worksite and access for construction of the authorised works
107, 111, 113, 115a, 116
Worksite and access for construction and maintenance of the authorised works
Provision of environmental mitigation
157
Diversion of utility apparatus
Provision of a new public right of way
175
Landscaping
Provision of a new public right of way
Diversion of utility apparatus
184
Landscaping
Provision of a new public right of way
223
Provision of environmental mitigation
227, 228
Provision of an electricity supply

---
Source: https://www.legislation.gov.uk/uksi/2018/923/schedule/2 (the official version)