# The Network Rail (West Coast Main Line) Order 2004, Paragraph 33


Subject to paragraph 35, if by reason of the construction of any specified work or of the failure of any such work the efficiency of any drainage work for flood defence purposes is impaired, or that work is otherwise damaged, such impairment or damage shall be made good by Network Rail to the reasonable satisfaction of the Agency and, if Network Rail fails to do so, the Agency may make good the same and recover from Network Rail the expense reasonably incurred by it in so doing.

---
Source: https://www.legislation.gov.uk/uksi/2004/389/schedule/13/paragraph/33 (the official version)
Page: https://openlegislation.uk/network-rail-west-coast-main-line-order-2004/schedule-13/paragraph-33
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.