# The Network Rail (West Coast Main Line) (Stowe Hill) Order 2006, Article 9: Time limit for exercise of powers of acquisition


No notice to treat shall be served under Part 1 of the 1965 Act, as applied to the acquisition of land by article 4 (application of Part 1 of Compulsory Purchase Act 1965), after the end of the period of 5 years beginning with the day on which this Order comes into force.

---
Source: https://www.legislation.gov.uk/uksi/2006/3471/article/9 (the official version)
Page: https://openlegislation.uk/network-rail-west-coast-main-line-stowe-hill-order-2006/article-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.