  "text": "(1) In this Part a “street” means the whole or any part of any of the following, irrespective of whether it is a thoroughfare—\n(a) any highway, road, lane, footway, alley or passage,\n(b) any square or court, and\n(c) any land laid out as a way whether it is for the time being formed as a way or not.\nWhere a street passes over a bridge or through a tunnel, references in this Part to the street include that bridge or tunnel.\n(2) The provisions of this Part apply to a street which is not a maintainable highway subject to such exceptions and adaptations as may be prescribed.\n(3) In this Part “street works” means works of any of the following kinds (other than works for road purposes) executed in a street in pursuance of a statutory right or a street works licence—\n(a) placing apparatus, or\n(b) inspecting, maintaining, adjusting, repairing, altering or renewing apparatus, changing the position of apparatus or removing it,\nor works required for or incidental to any such works (including, in particular, breaking up or opening the street, or any sewer, drain or tunnel under it, or tunnelling or boring under the street).\n(3ZA) In this Part “street works” also includes works of any of the following kinds executed in a street in England in pursuance of a street works permit—\n(a) placing apparatus that is a public charge point, or\n(b) inspecting, maintaining, adjusting, repairing, altering, renewing, changing the position of or removing apparatus that is a public charge point,\nor works required for or incidental to any such works (including, in particular, breaking up or opening the street, or any sewer, drain or tunnel under it, or tunnelling or boring under the street).\n(3A) For the purposes of subsection (3) or (3ZA), the works that are street works by virtue of being works required for or incidental to street works of any particular kind include—\n(a) reinstatement of the street, and\n(b) where an undertaker has failed to comply with his duties under this Part with respect to reinstatement of the street, any remedial works.\n(4) In this Part “undertaker” —\n(a) in relation to street works mentioned in subsection (3), means the person by whom the relevant statutory right is exercisable (in the capacity in which it is exercisable by him) or the licensee under the relevant street works licence, as the case may be;\n(b) in relation to street works described in subsection (3ZA), means the person who in accordance with the street works permit is permitted to carry out the works.\n(5) References in this Part to the undertaker in relation to apparatus in a street (including public charge points) are to the person entitled, by virtue of—\n(a) a statutory right,\n(b) a street works licence, or\n(c) where the apparatus is a public charge point installed in England in pursuance of a street works permit, the permit,\nto carry out in relation to the apparatus such works as are mentioned in subsection (3) or (3ZA); and references to an undertaker having apparatus in the street, or to the undertaker to whom apparatus belongs, shall be construed accordingly.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "S. 48(3ZA) inserted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(2), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "F",
      "label": "F2",
      "text": "S. 48(3A) inserted (26.1.2009) by Local Transport Act 2008 (c. 26), ss. 124(2), 134(2)"
    },
    {
      "type": "F",
      "label": "F3",
      "text": "Words in s. 48(3A) inserted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(3), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "F",
      "label": "F4",
      "text": "Words in s. 48(4) substituted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(4)(a), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "F",
      "label": "F5",
      "text": "S. 48(4)(b) inserted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(4)(b), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "F",
      "label": "F6",
      "text": "Words in s. 48(5) substituted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(5)(a), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "F",
      "label": "F7",
      "text": "Words in s. 48(5) inserted (13.3.2026) by Planning and Infrastructure Act 2025 (c. 34), ss. 49(5)(b), 118(1)(z5) (with s. 116); S.I. 2026/292, reg. 2"
    },
    {
      "type": "C",
      "label": "C1",
      "text": "S. 48(3) modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 10(2)"
    },
    {
      "type": "C",
      "label": "C2",
      "text": "S. 48(3) modified (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C3",
      "text": "S. 48(3) modified (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(2) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Pt. 2 para. 6, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)"
    },
    {
      "type": "C",
      "label": "C4",
      "text": "S. 48(3) modified (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(2) (with arts. 30(4), 53)"
    },
    {
      "type": "C",
      "label": "C5",
      "text": "S. 48(3) applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(2)"
    },
    {
      "type": "C",
      "label": "C6",
      "text": "S. 48(3) modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 10(2)(3) (with art. 32)"
    },
    {
      "type": "C",
      "label": "C7",
      "text": "S. 48(3) modified (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(2) (with art. 39)"
    },
    {
      "type": "C",
      "label": "C8",
      "text": "S. 48(3) modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(2) (with art. 31)"
    },
    {
      "type": "C",
      "label": "C9",
      "text": "S. 48(3) modified (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(2) (with arts. 6, 42)"
    },
    {
      "type": "C",
      "label": "C10",
      "text": "S. 48(3) modified (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C11",
      "text": "S. 48(3) modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(2) (with art. 37)"
    },
    {
      "type": "C",
      "label": "C12",
      "text": "S. 48(3) modified (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 10(2)"
    },
    {
      "type": "C",
      "label": "C13",
      "text": "S. 48(3) modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 11(5) (with art. 32, Sch. 9 para. 36)"
    },
    {
      "type": "C",
      "label": "C14",
      "text": "S. 48(3) modified (2.12.2021) by The South Humber Bank Energy Centre Order 2021 (S.I. 2021/1259), arts. 1, 10(2) (with Sch. 8 para. 48)"
    },
    {
      "type": "C",
      "label": "C15",
      "text": "S. 48(3) modified (13.7.2022) by The A47 Blofield to North Burlingham Development Consent Order 2022 (S.I. 2022/738), arts. 1, 15(2) (with arts. 4, 50)"
    },
    {
      "type": "C",
      "label": "C16",
      "text": "S. 48(3) modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 11(2) (with art. 4)"
    },
    {
      "type": "C",
      "label": "C17",
      "text": "S. 48(3) modified (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 9(2) (with art. 32, Sch. 10 paras. 26(2), 68)"
    },
    {
      "type": "C",
      "label": "C18",
      "text": "S. 48(3) modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 15(2) (with arts. 4, 50)"
    },
    {
      "type": "C",
      "label": "C19",
      "text": "S. 48(3) modified (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 8(2)"
    },
    {
      "type": "C",
      "label": "C20",
      "text": "S. 48(3) modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 10(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)"
    },
    {
      "type": "C",
      "label": "C21",
      "text": "S. 48(3) modified (3.8.2023) by The Hornsea Four Offshore Wind Farm Order 2023 (S.I. 2023/800), arts. 1, 8(2) (with arts. 42, 43, Sch. 9 Pt. 1 para. 4, Sch. 9 Pt. 3 para. 6(1), Sch. 9 Pt. 4 para. 20, Sch. 9 Pt. 9 para. 4)"
    },
    {
      "type": "C",
      "label": "C22",
      "text": "S. 48(3) modified (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 11(2) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))"
    },
    {
      "type": "C",
      "label": "C23",
      "text": "S. 48(3) modified (11.10.2023) by The Awel y Môr Offshore Wind Farm Order 2023 (S.I. 2023/1033), arts. 1, 9(2) (with arts. 36, 37, Sch. 9 paras. 14, 44(1), 76, 103)"
    },
    {
      "type": "C",
      "label": "C24",
      "text": "S. 48(3) modified (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), arts. 1, 9(2) (with art. 43, Sch. 12 paras. 5, 24)"
    },
    {
      "type": "C",
      "label": "C25",
      "text": "S. 48(3) modified (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 17(2) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)"
    },
    {
      "type": "C",
      "label": "C26",
      "text": "S. 48(3) modified (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 11(2) (with arts. 42, 43, Sch. 12 paras. 5, 51, 91, 129, 136, 234, 345, 356)"
    },
    {
      "type": "C",
      "label": "C27",
      "text": "S. 48(3) modified (13.3.2024) by The Medworth Energy from Waste Combined Heat and Poer Facility Order 2024 (S.I. 2024/230), arts. 1, 10 (with Sch. 11 paras. 5, 22, 37, 47, 82, 110)"
    },
    {
      "type": "C",
      "label": "C28",
      "text": "S. 48(3) modified (5.4.2024) by The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (S.I. 2024/393), arts. 1, 11(4) (with art. 44, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C29",
      "text": "S. 48(3) modified (11.4.2024) by The HyNet Carbon Dioxide Pipeline Order 2024 (S.I. 2024/436), arts. 1(2), 10(2) (with arts. 21, 41, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C30",
      "text": "S. 48(3) modified (9.5.2024) by The Sheringham Shoal and Dudgeon Extensions Offshore Wind Farm Order 2024 (S.I. 2024/564), arts. 1, 8(2) (with arts. 35, 36, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C31",
      "text": "S. 48(3) modified (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 13(2) (with art. 6, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C32",
      "text": "S. 48(3) modified (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), arts. 1, 8(2) (with Sch. 15)"
    },
    {
      "type": "C",
      "label": "C33",
      "text": "S. 48(3) modified (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), arts. 1, 8(2) (with art. 44, Sch. 12)"
    },
    {
      "type": "C",
      "label": "C34",
      "text": "S. 48(3) modified (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), arts. 1, 8(2) (with art. 45, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C35",
      "text": "S. 48(3) modified (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), arts. 1, 8(2) (with art. 48, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C36",
      "text": "S. 48(3) modified (4.10.2024) by The National Grid (Bramford to Twinstead Reinforcement) Order 2024 (S.I. 2024/958), arts. 1, 11(6) (with art. 40, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C37",
      "text": "S. 48(3) modified (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 11(2) (with art. 4, Sch. 10) (as amended by S.I. 2024/1020, Sch.)S. 48(3) modified (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), arts. 1, 8 (with art. 47, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C38",
      "text": "S. 48(3) modified (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), arts. 1, 8(2) (with art. 43, Sch. 13)"
    },
    {
      "type": "C",
      "label": "C39",
      "text": "S. 48(3) modified (27.2.2025) by The Associated British Ports (Immingham Green Energy Terminal) Order 2025 (S.I. 2025/165), arts. 1, 7(2) (with arts. 48, 59, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C40",
      "text": "S. 48(3) modified (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), arts. 1, 12(5) (with Sch. 14)"
    },
    {
      "type": "C",
      "label": "C41",
      "text": "S. 48(3) modified (28.4.2025) by The Rampion 2 Offshore Wind Farm Order 2025 (S.I. 2025/468), arts. 1, 9(2) (with arts. 47, 48, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C42",
      "text": "S. 48(3) modified (1.5.2025) by The Viking CCS Carbon Dioxide Pipeline Order 2025 (S.I. 2025/509), arts. 1(2), 9(2) (with art. 41, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C43",
      "text": "S. 48(3) modified (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), arts. 1, 8(2) (with art. 49, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C44",
      "text": "S. 48(3) modified (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 11(2) (with arts. 4, 43, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C45",
      "text": "S. 48(3) modified (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), arts. 1, 8(2) (with Sch. 10)"
    },
    {
      "type": "C",
      "label": "C46",
      "text": "S. 48(3) modified (28.7.2025) by The Mona Offshore Wind Farm Order 2025 (S.I. 2025/870), arts. 1, 10(2) (with arts. 37, 38, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C47",
      "text": "S. 48(3) modified (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 10(2) (with arts. 5, 34, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C48",
      "text": "S. 48(3) modified (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 11(2) (with arts. 5, 9(6), 43, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C49",
      "text": "S. 48(3) modified (22.10.2025) by The A46 Newark Bypass Development Consent Order 2025 (S.I. 2025/1090), arts. 1, 17(2) (with arts. 4, 9, 51, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C50",
      "text": "S. 48(3) modified (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), arts. 1, 8(2) (with art. 49, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C51",
      "text": "S. 48(3) modified (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), arts. 1, 10(2) (with art. 40, Sch. 13)"
    },
    {
      "type": "C",
      "label": "C52",
      "text": "S. 48(3) modified (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 13(2) (with Sch. 12)"
    },
    {
      "type": "C",
      "label": "C53",
      "text": "S. 48(3) modified (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), arts. 1, 9(2) (with Sch. 9)"
    },
    {
      "type": "C",
      "label": "C54",
      "text": "S. 48(3) modified (8.1.2026) by The Five Estuaries Offshore Wind Farm Order 2025 (S.I. 2025/1376), arts. 1, 10(2) (with arts. 39, 40, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C55",
      "text": "S. 48(3) modified (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 11(2) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 11(2) (with arts. 40, 45, Sch. 9))"
    },
    {
      "type": "C",
      "label": "C56",
      "text": "S. 48(3) modified (4.3.2026) by The Outer Dowsing Offshore Wind Farm Order 2026 (S.I. 2026/138), arts. 1(2), 8(2) (with arts. 42, 43, Sch. 18)"
    },
    {
      "type": "C",
      "label": "C57",
      "text": "S. 48(3) modified (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), arts. 1, 8(2) (with Sch. 14)"
    },
    {
      "type": "C",
      "label": "C58",
      "text": "S. 48(3) modified (30.4.2026) by The Springwell Solar Farm Order 2026 (S.I. 2026/419), arts. 1, 8(2) (with art. 48)"
    },
    {
      "type": "C",
      "label": "C59",
      "text": "S. 48(3) modified (5.6.2026) by The North Falls Offshore Wind Farm Order 2026 (S.I. 2026/567), arts. 1, 8(2) (with arts. 44, 45, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C60",
      "text": "S. 48(3) modified (5.6.2026) by The Dogger Bank South East and West Offshore Wind Farms Order 2026 (S.I. 2026/577), arts. 1, 8(2) (with arts. 40, 41, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C61",
      "text": "S. 48(3) modified (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 10(2) (with art. 37, Sch. 11)"
    },
    {
      "type": "C",
      "label": "C62",
      "text": "S. 48(3) modified (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 10(2) (with Sch. 13)"
    },
    {
      "type": "C",
      "label": "C63",
      "text": "S. 48(3) modified (30.7.2026) by The One Earth Solar Farm Order 2026 (S.I. 2026/934), arts. 1, 8(2) (with art. 47)"
    },
    {
      "type": "C",
      "label": "C64",
      "text": "S. 48(3) modified (14.9.2026) by The Beacon Fen Energy Park Order 2026 (S.I. 2026/1025), arts. 1, 11(2) (with art. 39, Sch. 11 para. 131)"
    },
    {
      "type": "C",
      "label": "C65",
      "text": "S. 48(3) modified (30.10.2026) by The Green Hill Solar Farm Order 2026 (S.I. 2026/1074), arts. 1, 8(2) (with Sch. 15)"
    },
    {
      "type": "C",
      "label": "C66",
      "text": "S. 48(3) modified (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 8(2) (with Sch. 10)"
    },
    {
      "type": "C",
      "label": "C67",
      "text": "Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)"
    },
    {
      "type": "C",
      "label": "C68",
      "text": "Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)"
    },
    {
      "type": "C",
      "label": "C69",
      "text": "Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)"
    },
    {
      "type": "C",
      "label": "C70",
      "text": "Pt. 3 modified (7.5.2014) by The National Grid (North London Reinforcement Project) Order 2014 (S.I. 2014/1052), arts. 1, 13(1)"
    },
    {
      "type": "C",
      "label": "C71",
      "text": "Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)"
    },
    {
      "type": "C",
      "label": "C72",
      "text": "Pt. 3 modified (9.2.2016) by The National Grid (Hinkley Point C Connection Project) Order 2016 (S.I. 2016/49), arts. 1, 11(1) (with art. 32)"
    },
    {
      "type": "C",
      "label": "C73",
      "text": "Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)"
    },
    {
      "type": "C",
      "label": "C74",
      "text": "Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)"
    },
    {
      "type": "C",
      "label": "C75",
      "text": "Pt. 3 modified (15.10.2020) by The Great Yarmouth Third River Crossing Development Consent Order 2020 (S.I. 2020/1075), arts. 1, 11(1)(2)"
    },
    {
      "type": "C",
      "label": "C76",
      "text": "Pt. 3 modified (29.10.2020) by The Southampton to London Pipeline Development Consent Order 2020 (S.I. 2020/1099), arts. 1, 12(1)(2) (with art. 32, Sch. 9 para. 36)"
    },
    {
      "type": "C",
      "label": "C77",
      "text": "Pt. 3 applied (2.12.2021) by The South Humber Bank Energy Centre Order 2021 (S.I. 2021/1259), arts. 1, 10(3) (with Sch. 8 para. 48)"
    },
    {
      "type": "C",
      "label": "C78",
      "text": "Pt. 3 modified (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(1)(2) (with art. 5)"
    },
    {
      "type": "C",
      "label": "C79",
      "text": "Pt. 3 modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(1)(2) (with art. 4)"
    },
    {
      "type": "C",
      "label": "C80",
      "text": "Pt. 3 modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(1)(2) (with arts. 4, 50)"
    },
    {
      "type": "C",
      "label": "C81",
      "text": "Pt. 3 modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)"
    },
    {
      "type": "C",
      "label": "C82",
      "text": "Pt. 3 modified (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(1)(2) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))"
    },
    {
      "type": "C",
      "label": "C83",
      "text": "Pt. 3 modified (9.2.2024) by The A12 Chelmsford to A120 Widening Development Consent Order 2024 (S.I. 2024/60), arts. 1, 12(1)(2) (with arts. 4, 52, Sch. 11 paras. 6, 24, 39(1), 55(1), 84)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/ukpga/1991/22/section/48",
    "retrieved_at": "2026-11-07T03:34:08.105882+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}