  "url": "https://openlegislation.uk/new-roads-and-street-works-act-1991/section-74B",
  "json_url": "https://openlegislation.uk/new-roads-and-street-works-act-1991/section-74B.json",
  "legislation": "ukpga/1991/22",
  "legislation_title": "New Roads and Street Works Act 1991",
  "legislation_url": "https://openlegislation.uk/new-roads-and-street-works-act-1991",
  "path": "section/74B",
  "kind": "section",
  "number": "74B",
  "heading": "Regulations under section 74 and regulations and orders under section 74B",
  "text": "(1) Nothing shall be taken to prevent the imposition of charges by both regulations under sections 74 and regulations under section 74A in respect of the execution of the same works at the same time.\n(2) The Secretary of State is the “appropriate person” in relation to an approval order which approves—\n(a) a strategic highways company, or\n(b) a local highway authority, unless a mayor is the appropriate person in relation to the order under any of subsections (3) to (5).\n(3) The Mayor of London is the “appropriate person” in relation to an approval order which approves—\n(a) Transport for London, or\n(b) a local highway authority whose area is within Greater London.\n(4) The mayor for the area of a mayoral combined authority is the “appropriate person” in relation to an approval order which approves a local highway authority whose area is within, or the same as, the area of the combined authority (including the combined authority).\n(5) The mayor for the area of mayoral CCA is the “appropriate person” in relation to an approval order which approves a local highway authority whose area is the same as, or is within, the area of the CCA (including the CCA).\n(6) But the mayor for the area of a mayoral combined authority or a mayoral CCA is not the appropriate authority in relation to an approval order if the application for that approval order is made on or before the day on which the first mayor for that area takes office; and accordingly—\n(a) the Secretary of State is (by virtue of subsection (2)(b)) the appropriate authority in relation to that approval order (and continues to be the appropriate authority in relation to that approval order after the first mayor takes office);\n(b) the application for that approval order must be made to the Secretary of State.\n(7) The Secretary of State may issue guidance about the approval of local highway authorities by the Mayor of London and the mayors for the areas of mayoral combined and mayoral CCAs; and—\n(a) local highway authorities must have regard to the guidance when seeking approval from the mayors;\n(b) the mayors must have regard to the guidance when considering whether to approve local highway authorities.\n(8) An approval order made by the Secretary of State is to be made by statutory instrument.\n(9) If a mayor makes an approval order, the mayor must publish the order in the manner which the mayor thinks is appropriate.\nThe power of a mayor to make an approval order includes the power to revoke, amend or re-enact any approval order made by the mayor or a predecessor.\n(10) The validity of an approval order approving a local highway authority (the “relevant authority”) which has been made by the Secretary of State (whether before or after the 2026 Act commencement) is not affected by the transfer of the power to approve the relevant authority.\n(11) The Secretary of State has the power, exercisable by order made by statutory instrument, to revoke such an order or to revoke it to the extent that it relates to the relevant authority.\n(12) In this section—\n“approval order” means an order under section 74A(2);\n“mayoral CCA” has the same meaning as in the English Devolution and Community Empowerment Act 2026 (see section 101 of that Act);\n“mayoral combined authority” has the same meaning as in the English Devolution and Community Empowerment Act 2026 (see section 101 of that Act);\n“transfer of the power to approve” means the power to make an order approving a local highway authority becoming exercisable by a mayor by virtue of this section, whether—\n(a)on the 2026 Act commencement (in relation to the Mayor of London or a mayoral combined authority or mayoral CCA existing at that commencement), or\n(b)subsequently (in relation to a mayoral combined authority or mayoral CCA that is established, or that becomes a mayoral combined authority or mayoral CCA, after the 2026 Act commencement);\n“2026 Act commencement” means the coming into force of paragraph 2 of Schedule 9 to the English Devolution and Community Empowerment Act 2026.",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Ss. 74A, 74B inserted (1.2.2001 subject to transitional provision and saving in Sch. 2 Pt. II of the commencing S.I.) by 2000 c. 38, s. 255(1); S.I. 2001/57, art. 3, Sch. 2 Pt. I (as amended by S.I. 2001/115, art. 2(5))"
    },
    {
      "type": "F",
      "label": "F2",
      "text": "S. 74B renumbered as s. 74B(1) (29.10.2026) by English Devolution and Community Empowerment Act 2026 (c. 23), s. 108(2)(6), Sch. 9 para. 2(2)(b) (with s. 102); S.I. 2026/1127, reg. 2(c)"
    },
    {
      "type": "F",
      "label": "F3",
      "text": "S. 74B(2)-(12) inserted (29.10.2026) by English Devolution and Community Empowerment Act 2026 (c. 23), s. 108(2)(6), Sch. 9 para. 2(2)(c) (with s. 102); S.I. 2026/1127, reg. 2(c)"
    },
    {
      "type": "F",
      "label": "F4",
      "text": "S. 74B heading substituted (29.10.2026) by English Devolution and Community Empowerment Act 2026 (c. 23), s. 108(2)(6), Sch. 9 para. 2(2)(a) (with s. 102); S.I. 2026/1127, reg. 2(c)"
    },
    {
      "type": "C",
      "label": "C1",
      "text": "Ss. 54-106 applied (28.2.2013) by The Rookery South (Resource Recovery Facility) Order 2011 2013 (S.I. 2013/680), art. 10(3)"
    },
    {
      "type": "C",
      "label": "C2",
      "text": "Pt. 3 applied (with modifications) (9.4.2013) by The Hinkley Point C (Nuclear Generating Station) Order 2013 (S.I. 2013/648), arts. 1, 9 (with arts. 48, 68, 79)"
    },
    {
      "type": "C",
      "label": "C3",
      "text": "Ss. 54-106 applied (9.4.2013) by The Lancashire County Council (Torrisholme to the M6 Link (A683 Completion of Heysham to M6 Link Road)) Order 2013 (S.I. 2013/675), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C4",
      "text": "Ss. 54-106 applied (15.6.2013) by The Galloper Wind Farm Order 2013 (S.I. 2013/1203), arts. 1, 13(3) (with arts. 11, 12)"
    },
    {
      "type": "C",
      "label": "C5",
      "text": "Ss. 54-106 applied (15.8.2013) by The North Blyth Biomass Power Station Order 2013 (S.I. 2013/1873), arts. 1, 9(3) (with art. 30)"
    },
    {
      "type": "C",
      "label": "C6",
      "text": "Ss. 54-106 applied (7.7.2014) by The East Anglia ONE Offshore Wind Farm Order 2014 (S.I. 2014/1599), arts. 1, 8(3) (with arts. 37, 38, Sch. 9 para. 19)"
    },
    {
      "type": "C",
      "label": "C7",
      "text": "Ss. 54-106 applied (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), arts. 1, 15(3) (with arts. 7(6), 12, 13, Sch. 12 Pt. 1 para. 19, Sch. 12 Pt. 2 para. 6, sch. 12 Pt. 3 para. 5, Sch. 12 Pt. 4 para. 4, Sch. 12 Pt. 5 para. 4)"
    },
    {
      "type": "C",
      "label": "C8",
      "text": "Pt. 3 restricted (6.8.2014) by The Rampion Offshore Wind Farm Order 2014 (S.I. 2014/1873), art. 1, Sch. 12 Pt. 2 para. 3 (with arts. 12, 13, Sch. 12 Pt. 1 paras. 6(3), 19, Pt. 2 paras. 3, 6, 13, Pt. 3 para. 5, Pt. 4 para. 4, Pt. 5 para. 4)"
    },
    {
      "type": "C",
      "label": "C9",
      "text": "Ss. 54-106 applied (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(4), 11(5) (with arts. 55, 56)"
    },
    {
      "type": "C",
      "label": "C10",
      "text": "Pt. 3 modified (24.9.2014) by The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), arts. 1, 10(5), 11(4)"
    },
    {
      "type": "C",
      "label": "C11",
      "text": "Ss. 54-106 applied (2.10.2014) by The North Killingholme (Generating Station) Order 2014 (S.I. 2014/2434), arts. 1, 9(3) (with arts. 6, 9(4), 13, Sch. 8 Pt. 1 para. 6, Sch. 8 Pt. 3 paras. 4(3), 6, 17, Sch. 8 Pt. 5 para. 9)"
    },
    {
      "type": "C",
      "label": "C12",
      "text": "Ss. 54-106 applied (29.10.2014) by The Able Marine Energy Park Development Consent Order 2014 (S.I. 2014/2935), art. 15(3) (with arts. 30(4), 53)"
    },
    {
      "type": "C",
      "label": "C13",
      "text": "Ss. 54-106 applied (28.11.2014) by The Walney Extension Offshore Wind Farm Order 2014 (S.I. 2014/2950), arts. 1, 10(3) (with arts. 38, 39)"
    },
    {
      "type": "C",
      "label": "C14",
      "text": "Ss. 54-106 applied (7.1.2015) by The Willington C Gas Pipeline Order 2014 (S.I. 2014/3328), arts. 1, 10(3)"
    },
    {
      "type": "C",
      "label": "C15",
      "text": "Ss. 54-106 applied (2.2.2015) by The Northumberland County Council (A1 – South East Northumberland Link Road (Morpeth Northern Bypass)) Development Consent Order 2015 (S.I. 2015/23), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C16",
      "text": "Ss. 54-106 applied (26.2.2015) by The Cornwall Council (A30 Temple to Higher Carblake Improvement) Order 2015 (S.I. 2015/147), arts. 1, 9(3)"
    },
    {
      "type": "C",
      "label": "C17",
      "text": "Ss. 54-106 applied (11.3.2015) by The Dogger Bank Creyke Beck Offshore Wind Farm Order 2015 (S.I. 2015/318), arts. 1, 13(3) (with arts. 8(5), 35, 40, 41, Sch. 12 Pt. 1 paras. 4, 9(2), 10, Pt. 2 paras. 4(2)(3), 19, Pt. 4 paras. 3, 4, 16)"
    },
    {
      "type": "C",
      "label": "C18",
      "text": "Ss. 54-106 applied (1.4.2015) by The Knottingley Power Plant Order 2015 (S.I. 2015/680), arts. 1, 10(3) (with art. 7(6), Sch. 8 para. 10)"
    },
    {
      "type": "C",
      "label": "C19",
      "text": "Ss. 54-106 applied (23.6.2015) by The Norfolk County Council (Norwich Northern Distributor Road (A1067 to A47(T))) Order 2015 (S.I. 2015/1347), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C20",
      "text": "Ss. 54-106 applied (30.6.2015) by The Swansea Bay Tidal Generating Station Order 2015 (S.I. 2015/1386), arts. 1, 9(3) (with arts. 51, 53)"
    },
    {
      "type": "C",
      "label": "C21",
      "text": "Ss. 54-106 applied (7.8.2015) by The Preesall Underground Gas Storage Facility Order 2015 (S.I. 2015/1561), arts. 1, 9(3) (with art. 44)"
    },
    {
      "type": "C",
      "label": "C22",
      "text": "Ss. 54-106 applied (14.8.2015) by The Progress Power (Gas Fired Power Station) Order 2015 (S.I. 2015/1570), arts. 1, 10(3)"
    },
    {
      "type": "C",
      "label": "C23",
      "text": "Ss. 54-106 applied (26.8.2015) by The Dogger Bank Teesside A and B Offshore Wind Farm Order 2015 (S.I. 2015/1592), arts. 1, 14(3) (with arts. 35, 40, 41)"
    },
    {
      "type": "C",
      "label": "C24",
      "text": "Ss. 54-106 applied (19.11.2015) by The Ferrybridge Multifuel 2 Power Station Order 2015 (S.I. 2015/1832), arts. 1(2), 9(3)"
    },
    {
      "type": "C",
      "label": "C25",
      "text": "Ss. 54-106 applied (30.12.2015) by The Port Talbot Steelworks Generating Station Order 2015 (S.I. 2015/1984), arts. 1, 9(3) (with art. 26)"
    },
    {
      "type": "C",
      "label": "C26",
      "text": "Ss. 54-106 applied (with modifications) (25.3.2016) by The Thorpe Marsh Gas Pipeline Order 2016 (S.I. 2016/297), arts. 1, 12(3) (with art. 39)"
    },
    {
      "type": "C",
      "label": "C27",
      "text": "Pt. 3 applied (with modifications) (2.8.2016) by The Midland Metro (Wolverhampton City Centre Extension) Order 2016 (S.I. 2016/684), arts. 1, 5(1)(2) (with arts. 46, 47, Sch. 8 para. 2(7), Sch. 9 para. 4, Sch. 10 para. 12(2))"
    },
    {
      "type": "C",
      "label": "C28",
      "text": "Ss. 54-106 applied (2.8.2016) by The Meaford Gas Fired Generating Station Order 2016 (S.I. 2016/779), arts. 1, 11(3)"
    },
    {
      "type": "C",
      "label": "C29",
      "text": "Ss. 54-106 applied (10.8.2016) by The York Potash Harbour Facilities Order 2016 (S.I. 2016/772), arts. 1, 10(3) (with arts. 35, 36)"
    },
    {
      "type": "C",
      "label": "C30",
      "text": "Ss. 54-106 applied (19.8.2016) by The North Wales Wind Farms Connection Order 2016 (S.I. 2016/818), arts. 1, 10(5) (with art. 35)"
    },
    {
      "type": "C",
      "label": "C31",
      "text": "Ss. 54-106 applied (with modifications) (15.9.2016) by The River Humber Gas Pipeline Replacement Order 2016 (S.I. 2016/853), arts. 1, 11(3) (with art. 43)"
    },
    {
      "type": "C",
      "label": "C32",
      "text": "Pt. 3 modified (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 9(2)"
    },
    {
      "type": "C",
      "label": "C33",
      "text": "Ss. 54-106 applied (23.9.2016) by The M4 Motorway (Junctions 3 to 12) (Smart Motorway) Development Consent Order 2016 (S.I. 2016/863), arts. 1, 11(3)"
    },
    {
      "type": "C",
      "label": "C34",
      "text": "Ss. 54-106 applied (27.9.2016) by The Triton Knoll Electrical System Order 2016 (S.I. 2016/880), arts. 1(2), 8(3) (with arts. 39, 40, Sch. 8 para. 19)"
    },
    {
      "type": "C",
      "label": "C35",
      "text": "Ss. 54-106 applied (18.3.2017) by The North London Heat and Power Generating Station Order 2017 (S.I. 2017/215), arts. 1, 10(3)"
    },
    {
      "type": "C",
      "label": "C36",
      "text": "Pt. 3 modified (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 12(1) (with art. 31)"
    },
    {
      "type": "C",
      "label": "C37",
      "text": "Ss. 54-106 applied (29.3.2017) by The Glyn Rhonwy Pumped Storage Generating Station Order 2017 (S.I. 2017/330), arts. 1, 10(3) (with art. 31)"
    },
    {
      "type": "C",
      "label": "C38",
      "text": "Ss. 54-106 applied (5.4.2017) by The Keuper Underground Gas Storage Facility Order 2017 (S.I. 2017/433), arts. 1, 10(4)"
    },
    {
      "type": "C",
      "label": "C39",
      "text": "Ss. 54-106 applied (8.8.2017) by The Wrexham Gas Fired Generating Station Order 2017 (S.I. 2017/766), arts. 1, 10(3)"
    },
    {
      "type": "C",
      "label": "C40",
      "text": "Ss. 54-106 applied (29.8.2017) by The East Anglia THREE Offshore Wind Farm Order 2017 (S.I. 2017/826), arts. 1, 8(3) (with arts. 5(9), 36, 37, Sch. 8 para. 34)"
    },
    {
      "type": "C",
      "label": "C41",
      "text": "Ss. 54-106 applied (12.10.2018) by The Eggborough Gas Fired Generating Station Order 2018 (S.I. 2018/1020), arts. 1, 8(3) (with arts. 6, 42)"
    },
    {
      "type": "C",
      "label": "C42",
      "text": "Ss. 54-106 applied (3.4.2019) by The Millbrook Gas Fired Generating Station Order 2019 (S.I. 2019/578), arts. 1, 9(3)"
    },
    {
      "type": "C",
      "label": "C43",
      "text": "Ss. 54-106 applied (10.10.2019) by The Abergelli Power Gas Fired Generating Station Order 2019 (S.I. 2019/1268), arts. 1, 9(3)"
    },
    {
      "type": "C",
      "label": "C44",
      "text": "Ss. 54-106 applied (25.10.2019) by The Drax Power (Generating Stations) Order 2019 (S.I. 2019/1315), arts. 1, 9(3)"
    },
    {
      "type": "C",
      "label": "C45",
      "text": "Ss. 54-106 applied (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 11(3) (with art. 3(1))"
    },
    {
      "type": "C",
      "label": "C46",
      "text": "Pt. 3 applied (with modifications) (27.2.2020) by The A30 Chiverton to Carland Cross Development Consent Order 2020 (S.I. 2020/121), arts. 1, 12(1)(2) (with art. 3(1))"
    },
    {
      "type": "C",
      "label": "C47",
      "text": "Ss. 54-106 applied (14.4.2020) by The Reinforcement to the North Shropshire Electricity Distribution Network Order 2020 (S.I. 2020/325), arts. 1, 10(4) (with art. 7)"
    },
    {
      "type": "C",
      "label": "C48",
      "text": "Ss. 54-106 applied (1.5.2020) by The Riverside Energy Park Order 2020 (S.I. 2020/419), arts. 1, 11(3) (with art. 7)"
    },
    {
      "type": "C",
      "label": "C49",
      "text": "Pt. 3 modified (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 13(1)(2) (with art. 37)"
    },
    {
      "type": "C",
      "label": "C50",
      "text": "Ss. 54-106 applied (11.6.2020) by The M42 Junction 6 Development Consent Order 2020 (S.I. 2020/528), arts. 1, 12(3) (with art. 37)"
    },
    {
      "type": "C",
      "label": "C51",
      "text": "Ss. 54-106 applied (1.9.2020) by The Immingham Open Cycle Gas Turbine Order 2020 (S.I. 2020/847), arts. 1, 9(3) (with Sch. 9 para. 144)"
    },
    {
      "type": "C",
      "label": "C52",
      "text": "Pt. 3 modified (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 10(1)(2) (with art. 5, Sch. 27 para. 36)"
    },
    {
      "type": "C",
      "label": "C53",
      "text": "Ss. 54-106 applied (9.2.2021) by The A1 Birtley to Coal House Development Consent Order 2021 (S.I. 2021/74), arts. 1, 12(3) (with art. 5, Sch. 27 para. 36)"
    },
    {
      "type": "C",
      "label": "C54",
      "text": "Ss. 54-106 applied (22.12.2021) by The Morlais Demonstration Zone Order 2021 (S.I. 2021/1478), arts. 1, 7, Sch. 10 para. 2 (with arts. 15, 50, Sch. 11 para. 29)"
    },
    {
      "type": "C",
      "label": "C55",
      "text": "Ss. 54-106 applied (10.3.2022) by The Thurrock Flexible Generation Plant Development Consent Order 2022 (S.I. 2022/157), arts. 1, 11(3) (with Sch. 8 Pt. 6 para. 19)"
    },
    {
      "type": "C",
      "label": "C56",
      "text": "Ss. 54-106 applied (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 14(4) (with arts. 15, 62, 76, 87)"
    },
    {
      "type": "C",
      "label": "C57",
      "text": "Ss. 54-106 applied (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 14(3) (with arts. 4, 53)"
    },
    {
      "type": "C",
      "label": "C58",
      "text": "Pt. 3 modified (11.8.2022) by The Sizewell C (Nuclear Generating Station) Order 2022 (S.I. 2022/853), arts. 1, 15(1) (with arts. 62, 76, 87)Pt. 3 modified (2.9.2022) by The A47 North Tuddenham to Easton Development Consent Order 2022 (S.I. 2022/911), arts. 1, 10(1)(2) (with arts. 4, 53)"
    },
    {
      "type": "C",
      "label": "C59",
      "text": "Ss. 54-106 applied (with modifications) (4.11.2022) by The A47/A11 Thickthorn Junction Development Consent Order 2022 (S.I. 2022/1070), arts. 1, 15(3) (with arts. 4, 52, Sch. 9 para. 82)"
    },
    {
      "type": "C",
      "label": "C60",
      "text": "Pt. 3 modified (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 11(1)(2) (with art. 5)"
    },
    {
      "type": "C",
      "label": "C61",
      "text": "Pt. 3 modified (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 12(1)(2) (with art. 4)"
    },
    {
      "type": "C",
      "label": "C62",
      "text": "Ss. 54-106 applied (7.12.2022) by The A57 Link Roads Development Consent Order 2022 (S.I. 2022/1206), arts. 1, 10(3) (with arts. 5, 11)"
    },
    {
      "type": "C",
      "label": "C63",
      "text": "Ss. 54-106 applied (7.12.2022) by The A417 Missing Link Development Consent Order 2022 (S.I. 2022/1248), arts. 1, 11(3) (with arts. 4, 12)"
    },
    {
      "type": "C",
      "label": "C64",
      "text": "Ss. 54-106 applied (29.12.2022) by The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022 (S.I. 2022/1396), arts. 1, 9(3) (with art. 32, Sch. 10 paras. 26(2), 68)"
    },
    {
      "type": "C",
      "label": "C65",
      "text": "Ss. 54-106 applied (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 15(3) (with arts. 4, 50)"
    },
    {
      "type": "C",
      "label": "C66",
      "text": "Pt. 3 modified (10.3.2023) by The A47 Wansford to Sutton Development Consent Order 2023 (S.I. 2023/218), arts. 1, 11(1)(2) (with arts. 4, 50)"
    },
    {
      "type": "C",
      "label": "C67",
      "text": "Ss. 54-106 applied (18.7.2023) by The Longfield Solar Farm Order 2023 (S.I. 2023/734), arts. 1, 8(3)"
    },
    {
      "type": "C",
      "label": "C68",
      "text": "Ss. 54-106 applied (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 10(3) (with arts. 5, 53, Sch. 8 paras. 6, 64)"
    },
    {
      "type": "C",
      "label": "C69",
      "text": "Pt. 3 modified (27.7.2023) by The Boston Alternative Energy Facility Order 2023 (S.I. 2023/778), arts. 1, 11(2) (with arts. 5, 53, Sch. 8 paras. 6, 64)"
    },
    {
      "type": "C",
      "label": "C70",
      "text": "Pt. 3 modified (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 12(1)(2) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))"
    },
    {
      "type": "C",
      "label": "C71",
      "text": "Ss. 54-106 applied (7.9.2023) by The A38 Derby Junctions Development Consent Order 2023 (S.I. 2023/923), arts. 1, 11(3) (with arts. 4, 45, Sch. 9 paras. 6, 46, 54(1))"
    },
    {
      "type": "C",
      "label": "C72",
      "text": "Ss. 54-106 applied (7.2.2024) by The Drax Power Station Bioenergy with Carbon Capture and Storage Extension Order 2024 (S.I. 2024/70), arts. 1, 9(3) (with art. 43, Sch. 12 paras. 5, 24)"
    },
    {
      "type": "C",
      "label": "C73",
      "text": "Ss. 54-106 applied (11.3.2024) by The Net Zero Teesside Order 2024 (S.I. 2024/174), arts. 1, 11(3) (with arts. 42, 43, Sch. 12 paras. 5, 51, 91, 129, 136, 234, 345, 356)"
    },
    {
      "type": "C",
      "label": "C74",
      "text": "Ss. 54-106 applied (13.3.2024) by The Medworth Energy from Waste Combined Heatnd Power Facility Order 2024 (S.I. 2024/230), arts. 1, 10 (with Sch. 11 paras. 5, 22, 37, 47, 82, 110)"
    },
    {
      "type": "C",
      "label": "C75",
      "text": "Ss. 54-106 applied (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 13(3) (with art. 6, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C76",
      "text": "Pt. 3 modified (14.6.2024) by The A1 in Northumberland: Morpeth to Ellingham Development Consent Order 2024 (S.I. 2024/733), arts. 1, 11(2) (with art. 6, Sch. 10)"
    },
    {
      "type": "C",
      "label": "C77",
      "text": "Ss. 54-106 applied (3.8.2024) by The Mallard Pass Solar Farm Order 2024 (S.I. 2024/796), arts. 1, 8(3) (with Sch. 15)"
    },
    {
      "type": "C",
      "label": "C78",
      "text": "Ss. 54-106 applied (3.8.2024) by The Gate Burton Energy Park Order 2024 (S.I. 2024/807), arts. 1, 8(3) (with art. 45, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C79",
      "text": "Ss. 54-106 applied (3.8.2024) by The Sunnica Energy Farm Order 2024 (S.I. 2024/802), arts. 1, 8(4) (with art. 44, Sch. 12)"
    },
    {
      "type": "C",
      "label": "C80",
      "text": "Ss. 54-106 applied (27.9.2024) by The Cottam Solar Project Order 2024 (S.I. 2024/943), arts. 1, 8(3) (with art. 48, Sch. 15)Ss. 54-106 applied (9.10.2024) by The M3 Junction 9 Development Consent Order 2024 (S.I. 2024/753), arts. 1, 11(3) (with arts. 4, 13, Sch. 10) (as amended by S.I. 2024/1020, Sch.)"
    },
    {
      "type": "C",
      "label": "C81",
      "text": "Ss. 54-106 applied (15.2.2025) by The West Burton Solar Project Order 2025 (S.I. 2025/116), arts. 1, 8 (with art. 47, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C82",
      "text": "Ss. 54-106 applied (17.2.2025) by The Heckington Fen Solar Park Order 2025 (S.I. 2025/85), arts. 1, 8(3) (with art. 43, Sch. 13)"
    },
    {
      "type": "C",
      "label": "C83",
      "text": "Ss. 54-106 applied (4.4.2025) by The North Lincolnshire Green Energy Park Order 2025 (S.I. 2025/362), arts. 1, 12(6) (with Sch. 14)"
    },
    {
      "type": "C",
      "label": "C84",
      "text": "Ss. 54-106 applied (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 10(3) (with Sch. 8 paras. 36(3), 87)"
    },
    {
      "type": "C",
      "label": "C85",
      "text": "Pt. 3 modified (24.4.2025) by The London Luton Airport Expansion Development Consent Order 2025 (S.I. 2025/463), arts. 1, 9(2) (with Sch. 8 paras. 36(3), 87)"
    },
    {
      "type": "C",
      "label": "C86",
      "text": "Ss. 54-106 applied (31.5.2025) by The East Yorkshire Solar Farm Order 2025 (S.I. 2025/585), arts. 1, 8(3) (with art. 49, Sch. 14)"
    },
    {
      "type": "C",
      "label": "C87",
      "text": "Ss. 54-106 applied (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 11(3) (with arts. 4, 43, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C88",
      "text": "Pt. 3 modified (25.6.2025) by The M5 Junction 10 Development Consent Order 2025 (S.I. 2025/795), arts. 1, 12(1)(2) (with arts. 4, 43, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C89",
      "text": "Ss. 54-106 applied (11.7.2025) by The Oaklands Farm Solar Park Order 2025 (S.I. 2025/739), arts. 1, 8(4) (with Sch. 10)"
    },
    {
      "type": "C",
      "label": "C90",
      "text": "Ss. 54-106 applied (30.9.2025) by The M60/M62/M66 Simister Island Interchange Development Consent Order 2025 (S.I. 2025/1018), arts. 1, 10(3) (with arts. 5, 34, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C91",
      "text": "Ss. 54-106 applied (12.10.2025) by The Gatwick Airport (Northern Runway Project) Development Consent Order 2025 (S.I. 2025/1054), arts. 1, 11(3) (with arts. 5, 9(6), 43, Sch. 9)"
    },
    {
      "type": "C",
      "label": "C92",
      "text": "Ss. 54-106 applied (5.11.2025) by The Tillbridge Solar Order 2025 (S.I. 2025/1105), arts. 1, 8(3) (with art. 49, Sch. 15)"
    },
    {
      "type": "C",
      "label": "C93",
      "text": "Ss. 54-106 applied (13.11.2025) by The Stonestreet Green Solar Order 2025 (S.I. 2025/1175), arts. 1, 10(3) (with art. 40, Sch. 13)"
    },
    {
      "type": "C",
      "label": "C94",
      "text": "Ss. 54-106 applied (27.11.2025) by The Cory Decarbonisation Project Order 2025 (S.I. 2025/1227), arts. 1, 13(3) (with Sch. 12)"
    },
    {
      "type": "C",
      "label": "C95",
      "text": "Ss. 54-106 applied (29.12.2025) by The Helios Renewable Energy Project Order 2025 (S.I. 2025/1372), arts. 1, 9(3) (with Sch. 9)"
    },
    {
      "type": "C",
      "label": "C96",
      "text": "Ss. 54-106 applied (25.2.2026) by The A46 Coventry Junctions (Walsgrave) Development Consent Order 2026 (S.I. 2026/125), arts. 1, 11(3) (with arts. 40, 45, Sch. 9) (which affecting provisions were superseded by S.I. 2026/537, arts. 1, 11(3) (with arts. 40, 45, Sch. 9))"
    },
    {
      "type": "C",
      "label": "C97",
      "text": "Ss. 54-106 applied (11.3.2026) by The Fenwick Solar Farm Order 2026 (S.I. 2026/151), arts. 1, 8(3) (with Sch. 14)"
    },
    {
      "type": "C",
      "label": "C98",
      "text": "Ss. 54-106 applied (30.4.2026) by The Springwell Solar Farm Order 2026 (S.I. 2026/419), arts. 1, 8(3) (with art. 48)"
    },
    {
      "type": "C",
      "label": "C99",
      "text": "Ss. 54-106 applied (23.7.2026) by The Peartree Hill Solar Farm Order 2026 (S.I. 2026/869), arts. 1, 10(3) (with art. 37, Sch. 11)"
    },
    {
      "type": "C",
      "label": "C100",
      "text": "Ss. 54-106 applied (24.7.2026) by The Dean Moor Solar Farm Order 2026 (S.I. 2026/754), arts. 1, 10(3) (with Sch. 13)"
    },
    {
      "type": "C",
      "label": "C101",
      "text": "Ss. 54-106 applied (30.7.2026) by The One Earth Solar Farm Order 2026 (S.I. 2026/934), arts. 1, 8(3) (with art. 47)"
    },
    {
      "type": "C",
      "label": "C102",
      "text": "Ss. 54-106 applied (14.9.2026) by The Beacon Fen Energy Park Order 2026 (S.I. 2026/1025), arts. 1, 11(3) (with art. 39, Sch. 11 para. 131)"
    },
    {
      "type": "C",
      "label": "C103",
      "text": "Ss. 54-106 applied (30.10.2026) by The Green Hill Solar Farm Order 2026 (S.I. 2026/1074), arts. 1, 8(3) (with Sch. 15)"
    },
    {
      "type": "C",
      "label": "C104",
      "text": "Ss. 54-106 applied (31.10.2026) by The Steeple Renewables Project Order 2026 (S.I. 2026/1086), arts. 1, 8(3) (with Sch. 10)"
    },
    {
      "type": "C",
      "label": "C105",
      "text": "Pt. 3 modified (11.2.2005) by The Merseytram (Liverpool City Centre to Kirkby) Order 2005 (S.I. 2005/120), arts. 1, 4(1)(2) (with arts. 65, 66)"
    },
    {
      "type": "C",
      "label": "C106",
      "text": "Pt. 3 modified (22.3.2005) by The Midland Metro (Wednesbury to Brierley Hill and Miscellaneous Amendments) Order 2005 (S.I. 2005/927), art. 3(1)(2) (with art. 51)"
    },
    {
      "type": "C",
      "label": "C107",
      "text": "Pt. 3 modified (22.7.2005) by The Midland Metro (Birmingham City Centre Extension, etc.) Order 2005 (S.I. 2005/1794), arts. 1, 3(1)(2) (with art. 47)"
    },
    {
      "type": "C",
      "label": "C108",
      "text": "Pt. 3 applied (3.8.2005) by The Greater Manchester (Leigh Busway) Order 2005 (S.I. 2005/1918), arts. 1, 3(1)"
    },
    {
      "type": "C",
      "label": "C109",
      "text": "Pt. 3 modified (26.8.2005) by The River Tyne (Tunnels) Order 2005 (S.I. 2005/2222), arts. 1, 8(7) (with arts. 45(1), 48, Sch. 10 paras. 21, 29)"
    },
    {
      "type": "C",
      "label": "C110",
      "text": "Pt. 3 restricted (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 10(3)"
    },
    {
      "type": "C",
      "label": "C111",
      "text": "Pt. 3 modified (8.10.2005) by The Leicestershire County Council (Ashby de la Zouch Canal Extension) Order 2005 (S.I. 2005/2786), arts. 1, 9(1)"
    },
    {
      "type": "C",
      "label": "C112",
      "text": "Pt. 3 modified (25.11.2005) by The Docklands Light Railway (Capacity Enhancement) Order 2005 (S.I. 2005/3105), arts. 1, 3(1) (with arts. 3(5), 15(3))"
    },
    {
      "type": "C",
      "label": "C113",
      "text": "Pt. 3 applied (11.1.2006) by The Cambridgeshire Guided Busway Order 2005 (S.I. 2005/3523), arts. 1, 3(1) (with art. 52)"
    },
    {
      "type": "C",
      "label": "C114",
      "text": "Pt. 3 modified (1.2.2011) by The River Mersey (Mersey Gateway Bridge) Order 2011 (S.I. 2011/41), arts. 1, 3(1) (with art. 51, Sch. 10 paras. 68, 85)"
    },
    {
      "type": "C",
      "label": "C115",
      "text": "Pt. 3 modified (9.1.2014) by The National Grid (King’s Lynn B Power Station Connection) Order 2013 (S.I. 2013/3200), arts. 1, 9(1)"
    },
    {
      "type": "C",
      "label": "C116",
      "text": "Pt. 3 applied (with modifications) (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(9) (with arts. 57, 58, Sch. 11 para. 19)"
    },
    {
      "type": "C",
      "label": "C117",
      "text": "Pt. 3 modified (9.1.2014) by The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013 (S.I. 2013/3244), arts. 1, 4(1)(2) (with arts. 57, 58, Sch. 11 para. 19)"
    },
    {
      "type": "C",
      "label": "C118",
      "text": "Pt. 3 modified (12.1.2016) by The London Underground (Bank Station Capacity Upgrade) Order 2015 (S.I. 2015/2044), arts. 1, 4(1)(2)"
    },
    {
      "type": "C",
      "label": "C119",
      "text": "Pt. 3 applied (with modifications) (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)"
    },
    {
      "type": "C",
      "label": "C120",
      "text": "Pt. 3 modified (2.1.2018) by The Boston Barrier Order 2017 (S.I. 2017/1329), arts. 1, 3(2) (with arts. 55-57, Sch. 8 para. 13)"
    },
    {
      "type": "C",
      "label": "C121",
      "text": "Pt. 3 modified (25.2.2020) by The Network Rail (East West Rail) (Bicester to Bedford Improvements) Order 2020 (S.I. 2020/114), arts. 1, 4(1) (with art. 37(2))"
    },
    {
      "type": "C",
      "label": "C122",
      "text": "Pt. 3 modified (18.6.2020) by The A63 (Castle Street Improvement, Hull) Development Consent Order 2020 (S.I. 2020/556), arts. 1, 9(1)(2) (with arts. 5, 44)"
    },
    {
      "type": "C",
      "label": "C123",
      "text": "Pt. 3 modified (2.6.2022) by The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022 (S.I. 2022/549), arts. 1, 11(1)(2) (with arts. 6, 34)"
    },
    {
      "type": "C",
      "label": "C124",
      "text": "Pt. 3 modified (6.6.2022) by The M25 Junction 28 Development Consent Order 2022 (S.I. 2022/573), arts. 1, 10(1)(2) (with arts. 5, 36) (as amended (7.2.2024) by S.I. 2024/129, art. 1, Sch.)"
    },
    {
      "type": "C",
      "label": "C125",
      "text": "Pt. 3 modified (5.12.2022) by The Portishead Branch Line (MetroWest Phase 1) Order 2022 (S.I. 2022/1194), arts. 1, 12(1)(2) (with art. 51)"
    },
    {
      "type": "C",
      "label": "C126",
      "text": "Pt. 3 modified (11.1.2023) by The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022 (S.I. 2022/1406), arts. 1, 4(1) (with art. 34(2), Sch. 12 paras. 5, 47, 79)"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/ukpga/1991/22/section/74B",
    "retrieved_at": "2026-11-07T03:34:08.105882+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}