# The Non-Domestic Rating (Renewable Energy Projects) Regulations 2013, Regulation 6: Class A: new renewable power stations

Extent: E+W

(1) Class A consists of any hereditament in relation to which the conditions in paragraph (2) are fulfilled.
(2) The conditions mentioned in paragraph (1) are that—
(a) the hereditament is a renewable power station;
(b) the hereditament is first entered onto a local non-domestic rating list for the area of a billing authority in England on or after 1st April 2013; and
(c) neither Schedule 1 or 2 applies.

---
Source: https://www.legislation.gov.uk/uksi/2013/108/regulation/6 (the official version)