OpenLegislation

Introductory text

Original text. Later amendments are not shown.

Infrastructure Planning

Made 11th August 2022

Coming into force 12th August 2022

The Norfolk Boreas Offshore Wind Farm Order 2021 (“the Order”)f1, which granted development consent within the meaning of the Planning Act 2008 (“the Act”)f2, contained correctable errors within the meaning of the Actf3.

In accordance with paragraph 1(5)(a) of Schedule 4 to the Act, and before the end of the relevant period (as defined in paragraph 1(6)(a) of Schedule 4 to the Act), the Secretary of State received a written request from the applicantf4 for the correction of errors and omissions in the Order.

The Secretary of State has informed the relevant local planning authorities to which the Order relates, that the request has been received in accordance with paragraph 1(7) of Schedule 4 to the Act.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order—

Annotations

Footnotes

f1

S.I. 2021/1414.

f2

2008 c. 29. Paragraph 1 of Schedule 4 was amended by paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and by paragraph 4 of Schedule 8 to the Marine and Coastal Access Act 2009 (c. 23). There are other amendments to the Act which are not relevant to this Order.

f3

As provided for in paragraph 1(3) of Schedule 4 to the Act.

f4

As defined in paragraph 4 of Schedule 4 to the Act.