# The Norfolk Boreas Offshore Wind Farm Order 2021, Article 12: Access to works

Extent: E+W

(1) The undertaker may, for the purposes of the authorised project—
(a) form and lay out means of access, or improve existing means of access, in the locations specified in columns (1) and (2) of Part 1 of Schedule 5 (access to works) in the event of scenario 1, or columns (1) and (2) of Part 2 of Schedule 5 (access to works) in the event of scenario 2; and
(b) with the approval of the relevant planning authority after consultation with the highway authority in accordance with requirement 22 (highway accesses), form and lay out such other means of access or improve existing means of access, at such locations within the Order limits as the undertaker reasonably requires for the purposes of the authorised project.
(2) If the relevant planning authority fails to notify the undertaker of its decision within 28 days of receiving an application for approval under paragraph (1)(b) that relevant planning authority is deemed to have granted approval.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/article/12 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/article-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.