# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 15: Scenarios, stages, and phases of authorised development onshore

Extent: E+W

(1) Subject to paragraph (2), the undertaker may commence, or exercise powers of compulsory acquisition under Part 5 of this Order in relation to, only:
(a) scenario 1; or
(b) scenario 2.
(2) In the event that the Norfolk Vanguard Offshore Wind Farm is commenced, the undertaker may only commence scenario 1 and, for the avoidance of doubt, must not commence scenario 2.
(3) The onshore transmission works must not commence, nor powers of compulsory acquisition under Part 5 of this Order be exercised, until notification has been submitted to the relevant planning authority:
(a) as to whether the undertaker intends to commence scenario 1 or scenario 2; and
(b) detailing whether the onshore transmission works will be constructed in a single onshore phase or in two onshore phases.
(4) The onshore transmission works must not commence until a written scheme setting out the stages of the onshore transmission works for the relevant onshore phase has been submitted to the relevant planning authority, which scheme may subsequently be amended from time to time as notified to the relevant planning authority.
(5) The written scheme must be implemented as notified under paragraph (4).
(6) In paragraph (2) of this requirement, “commenced” in relation to the Norfolk Vanguard Offshore Wind Farm has the same meaning as provided for in any development consent order that may be made by the Secretary of State in relation to the Norfolk Vanguard Offshore Wind Farm..

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/1/paragraph/15 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-1/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.