# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 8: Detailed offshore design parameters

Extent: E+W

(1) In relation to an offshore electrical platform, each foundation using piles must not have—
(a) more than 18 driven piles; or
(b) in the case of two or more pile structures, have a pile diameter which is more than five metres.
(2) In relation to the offshore electrical platform(s), the foundations must not have a combined seabed footprint area (excluding scour protection) of greater than 15,000 m2.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/1/paragraph/8 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-1/paragraph-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.