# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 12: Construction monitoring

Extent: E+W

(1) The undertaker must, in discharging condition 7(1)(b), submit details (which accord with the offshore in principle monitoring plan) for approval by the MMO in consultation with the relevant statutory nature conservation bodies of any proposed monitoring, including methodologies and timings, to be carried out during the construction of the authorised scheme. The survey proposals must specify each survey’s objectives.
(2) The undertaker must carry out the surveys approved under sub-paragraph (1) and provide the agreed reports in the agreed format in accordance with the agreed timetable, unless otherwise agreed in writing with the MMO in consultation with the relevant statutory nature conservation bodies.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/13/paragraph/12 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-13/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.