# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 14: Reporting of cable protection

Extent: E+W

(1) Not more than 4 months following completion of the construction phase of the authorised scheme, the undertaker must provide the MMO and the relevant statutory nature conservation bodies with a report setting out details of the cable protection used for the authorised scheme.
(2) The report must include the following information—
(a) location of the cable protection;
(b) volume of cable protection; and
(c) any other information relating to the cable protection as agreed between the MMO and the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/13/paragraph/14 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-13/paragraph-14