# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 15: Coordination with Norfolk Vanguard Offshore Wind Farm

Extent: E+W

(1) Prior to submission of each of the pre-construction plans and documentation required to be submitted under condition 7(1) above the undertaker must provide a copy of the relevant plans and documentation to the undertaker of the offshore element of the Norfolk Vanguard Offshore Wind Farm to enable that undertaker to provide any comments on the plans and documentation.
(2) The undertaker must participate in liaison meetings with the undertaker of the offshore element of the Norfolk Vanguard Offshore Wind Farm as requested from time to time by the MMO in writing in advance, which meeting will be chaired by the MMO and may consider such matters as are determined by the MMO relating to the efficient operation of the offshore element of the authorised project and the offshore element of the Norfolk Vanguard Offshore Wind Farm.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/13/paragraph/15 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-13/paragraph-15
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.