# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 1: Effect of this licence

Extent: E+W

(1) This licence takes effect in the event of scenario 1 only.
(2) The undertaker may only commence either Work No. 3B or Work No. 3A and, for the avoidance of doubt, must not commence both of Work No. 3B and Work No. 3A.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/13/part/4/paragraph/1 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-13/part-4/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.