# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 68

Extent: E+W

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 37 (certification of plans etc.) are certified by the Secretary of State, provide a set of those plans to Network Rail in electronic form specified by Network Rail.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/17/paragraph/68 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-17/paragraph-68
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.