# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 69

Extent: E+W

In relation to any dispute arising under this Part that is referred to arbitration in accordance with article 38 (arbitration) of the Order, the parties agree that the timetable referred to within Paragraph 3 of Schedule 15 (Arbitration Rules) will be amended where Network Rail can demonstrate that it is unable (acting reasonably) to comply with the time limit due to timing constraints that may arise for Network Rail in obtaining clearance conditions and/or any engineering regulatory or stakeholder (internal or external) consents and/or assessing any matters of concern with regards to the safe operation of the railway.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/17/paragraph/69 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-17/paragraph-69
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.