# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 14

Extent: E+W

Following consultation with the LBBGSG, the LBBGIMP must be submitted to and approved by the Secretary of State, in consultation with the local planning authority or authorities for the land containing the predator control fencing, and the relevant statutory nature conservation body. The LBBGSG must be consulted further as required during the approval process.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/19/paragraph/14 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-19/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.