# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 28

Extent: E+W

The BIMP must accord with the relevant principles contained in the HHW SAC compensation plan, must contain the relevant matters identified in paragraph 141 of the HHW SAC compensation plan and must include provision for:
(a) the identification and retrieval of marine debris; and
(b) education, awareness and facilities to limit further marine debris,
which are described as Strand 2 and Strand 3 respectively in section 4.3.4 of the HHW SAC compensation plan.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/19/paragraph/28 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-19/paragraph-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.