# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 37


Following receipt of any application pursuant to paragraph 35, the Secretary of State must be satisfied—
(a) that the application to use the Marine Recovery Fund as an adaptive management measure is acceptable in principle including (if relevant) the exact proportion of the original compensation for which a Marine Recovery Fund Payment can be accepted in substitution; and
(b) that Defra or any other organisation responsible for the operation of the Marine Recovery Fund has confirmed that the Marine Recovery Fund can be used, such confirmation to include monetary quantification of the sums due in lieu of the compensation measures.

---