# The Norfolk Boreas Offshore Wind Farm Order 2021, Part 3: Permanent stopping up of private means of access for which a substitute is to be provided – Scenario 1

Extent: E+W

(1)
Area
(2)
Private means of access to be stopped
(3)
Extent of stopping up
(4)
New private means of access to be substituted or provided
District of Breckland
Vehicular access in the vicinity of the Necton National Grid substation
Private access to the fields to the north and east of Necton National Grid Substation, a distance of 380 metres, shown by a purple line between points marked A and B on the private means of access to be permanently stopped up plan.
A new private access to the fields north and east of the Necton National Grid substation from private track off the A47 as shown by a green line between points marked A and B on the private means of access to be permanently stopped up plan.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/4/part/3 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-4/part-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.