# The Norfolk Boreas Offshore Wind Farm Order 2021, Paragraph 23: Completion of construction

Extent: E+W

(1) The undertaker must submit a close out report to the MMO and the relevant statutory nature conservation body within three months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
(a) the final number of installed turbine generators;
(b) the installed wind turbine generator parameters relevant for ornithological collision risk modelling.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.

---
Source: https://www.legislation.gov.uk/uksi/2021/1414/schedule/9/paragraph/23 (the official version)
Page: https://openlegislation.uk/norfolk-boreas-offshore-wind-farm-order-2021/schedule-9/paragraph-23
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

