Within 30 days of anticipated completion of the authorised works, the undertaker shall provide written notice to Trinity House of the date of anticipated completion. The undertaker shall provide Trinity House with written confirmation of the date of completion of the authorised works not later than 1 day following completion of the authorised works (the “completion notice”).