# The Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023

S.I. 2023/1390 · made 13 December 2023

This Order amends the Norfolk Vanguard Offshore Wind Farm Order 2022, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008.

Made under: Planning Act 2008 (Schedule 6 paragraph 2)

PDFs: Printed copy https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-amendment-order-2023/pdf/uksi_20231390_en.pdf

## Introductory text

Infrastructure Planning
Made 13th December 2023
Coming into force 14th December 2023
An application has been made, under paragraph 2 of Schedule 6 to the Planning Act 2008, to the Secretary of State in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 (“the 2011 Regulations”) for a non-material change to the Norfolk Vanguard Offshore Wind Farm Order 2022.
The Secretary of State, having considered the application, the responses to the publicity and consultation required by regulations 6 and 7 of the 2011 Regulations , has decided to make the change on terms that in the opinion of the Secretary of State are not materially different from those proposed in the application.
Accordingly, the Secretary of State, in exercise of the powers in paragraph 2(1) and (9) of Schedule 6 to the Planning Act 2008, makes the following Order:

## 1 Citation and commencement

This Order may be cited as the Norfolk Vanguard Offshore Wind Farm (Amendment) Order 2023 and comes into force on 14th December 2023.

## 2 Amendment to The Norfolk Vanguard Offshore Wind Farm Order 2022

The Norfolk Vanguard Offshore Wind Farm Order 2022 is amended in accordance with this Order.

## 3 Amendment to Part 3 (Requirements) of Schedule 1 (Authorised Project)

In Part 3 (Requirements) of Schedule 1 (Authorised Project), in paragraph 16(18), for “must not exceed two” substitute “must not exceed four”.

## Signature

Signed by authority of the Secretary of State for Energy, Security and Net Zero
John Wheadon
Head of Energy Infrastructure Planning Delivery
Department for Energy, Security and Net Zero
13th December 2023

## Explanatory note

(This note is not part of the Order)
This Order amends the Norfolk Vanguard Offshore Wind Farm Order 2022, a development consent order under the Planning Act 2008, following an application made in accordance with the Infrastructure Planning (Changes to, and Revocation of, Development Consent Orders) Regulations 2011 for a non-material change under paragraph 2 of Schedule 6 to the Planning Act 2008.

---
Source: https://www.legislation.gov.uk/uksi/2023/1390 (the official version)
Page: https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-amendment-order-2023
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.