# The Norfolk Vanguard Offshore Wind Farm Order 2020, Article 3: Development consent etc. granted by the Order

Extent: E+W+S

(1) Subject to the provisions of this Order and to the requirements the undertaker is granted—
(a) Development consent for the authorised development; and
(b) Consent for the ancillary works,
to be carried out within the Order limits.
(2) Subject to the requirements and conditions in the deemed marine licences, Work Nos. 1 to 4B must be constructed anywhere within the Order limits seaward of MHWS and Work Nos. 4C to 12 must be constructed anywhere within the Order limits landward of MHWS.

---