{
  "url": "https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-order-2020/schedule-1/paragraph-15",
  "json_url": "https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-order-2020/schedule-1/paragraph-15.json",
  "legislation": "uksi/2020/706",
  "legislation_title": "The Norfolk Vanguard Offshore Wind Farm Order 2020",
  "legislation_url": "https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-order-2020",
  "path": "schedule/1/paragraph/15",
  "kind": "paragraph",
  "number": "15",
  "heading": "Stages of authorised development onshore",
  "text": "(1) The onshore transmission works may not be commenced until notification has been submitted to the relevant planning authority detailing whether the onshore works will be constructed:\n(a) in a single onshore phase; or\n(b) in two onshore phases.\n(2) The onshore transmission works may not be commenced until a written scheme setting out the stages of the onshore transmission works for the relevant onshore phase has been submitted to the relevant planning authority.\n(3) The written scheme must be implemented as notified under paragraph 2.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 1 para. 15 in force at 22.7.2020, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2020/706/schedule/1/paragraph/15",
    "retrieved_at": "2026-10-28T22:28:26.855626+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}