# The Norfolk Vanguard Offshore Wind Farm Order 2022, Paragraph 11: Detailed offshore design parameters

Extent: E+W+S

The total amount of scour protection for the wind turbine generators, accommodation platform, meteorological masts, offshore electrical platforms and LIDAR measurement buoys forming part of the authorised project must not exceed 5,196,703m2 and 25,983,515m3.

---