# The Norfolk Vanguard Offshore Wind Farm Order 2022, Paragraph 2: Design parameters

Extent: E+W+S

The total length of the cables and the area and volume of their cable protection must not exceed the following—
Work
Length
Cable protection (m2 and m3)
Work No. 3 (Interconnector link)
150 kilometres
76,000m2 38,000 m3
Work No. 4A and 4B (export cable)
400 kilometres
102,086m2 59,836 m3

---