# The Norfolk Vanguard Offshore Wind Farm Order 2022, Paragraph 7: Design parameters

Extent: E+W+S

(1) In relation to any LIDAR measurement buoys, each foundation using piles must not have a pile diameter of greater than 10 metres.
(2) In relation to any LIDAR measurement buoys, each foundation must not have a seabed footprint area (excluding scour protection) of greater than 79m² per buoy and 157 m2 in total.
(3) In relation to any wave measurement buoys, each foundation must not have a seabed footprint area (excluding scour protection) of greater than 150m² per buoy and 300 m2 in total.

---
Source: https://www.legislation.gov.uk/uksi/2022/138/schedule/9/paragraph/7 (the official version)
Page: https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-order-2022/schedule-9/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.