# The Norfolk Vanguard Offshore Wind Farm Order 2022, Paragraph 3: Design parameters

Extent: E+W+S

The total length of the cables and the area and volume of their cable protection must not exceed the following—
Work
Length
Cable protection (m2 and m3)
Work No. 1(e) (array)
600 kilometres
389,000m2 198,500 m3

---
Source: https://www.legislation.gov.uk/uksi/2022/138/schedule/9/part/4/paragraph/3 (the official version)
Page: https://openlegislation.uk/norfolk-vanguard-offshore-wind-farm-order-2022/schedule-9/part-4/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.