# The North Blyth Biomass Power Station Order 2013, Article 14: Compulsory acquisition of land – incorporation of the minerals code


Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981 (minerals) are incorporated in this Order subject to the modifications that—
(a) paragraph 8(3) is not incorporated; and
(b) for “the acquiring authority” substitute “the undertaker”.

---