# The North Blyth Biomass Power Station Order 2013, Article 28: Certification of plans etc


(1) The undertaker shall, as soon as practicable after the making of this Order, submit to the Secretary of State copies of—
(a) the book of reference;
(b) the design and access statement;
(c) the elevations plan;
(d) the environmental statement;
(e) the heat radiation contour plan;
(f) the land plan;
(g) the massing plan; and
(h) the works plan
for certification that they are true copies of the documents referred to in this Order.
(2) A plan or document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.

---
Source: https://www.legislation.gov.uk/uksi/2013/1873/article/28 (the official version)
Page: https://openlegislation.uk/north-blyth-biomass-power-station-order-2013/article-28
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.