# The North Blyth Biomass Power Station Order 2013, Paragraph 32: Waste management on site


(1) The authorised development may not be brought in to first commercial use until the relevant planning authority has received and approved in writing a site waste management plan for the operational phases of the authorised development incorporating the principles in paragraphs 4.4.23 to 4.4.26 of the environmental statement. The site waste management plan must address and include at least the following—
(a) the storage of waste materials on site;
(b) removal of waste materials from the site for recovery/disposal at appropriately licensed sites; and
(c) the return/disposal of general engineering wastes (such as spent filters and used parts).
(2) The authorised development must thereafter be operated fully in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2013/1873/schedule/2/paragraph/32 (the official version)
Page: https://openlegislation.uk/north-blyth-biomass-power-station-order-2013/schedule-2/paragraph-32
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.