(1) No part of the authorised development may commence until written details of the siting, design and layout of any new permanent or temporary means of access to a highway to be used by vehicular traffic, or any alteration to an existing means of access to a highway used by vehicular traffic, has, after consultation with the relevant planning authority and highway authority, been submitted to and approved by the relevant planning authority.
(2) The highway accesses must be constructed in accordance with the approved details prior to first commercial use of the authorised development.

---