# The North Blyth Biomass Power Station Order 2013, Paragraph 43: Amendments to approved details


With respect to any of the Requirements which require the authorised development to be carried out in accordance with the details approved by the relevant planning authority, the approved details must be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2013/1873/schedule/2/paragraph/43 (the official version)
Page: https://openlegislation.uk/north-blyth-biomass-power-station-order-2013/schedule-2/paragraph-43
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.