OpenLegislation

Article 3 Development consent etc. granted by this Order

Original text. Later amendments are not shown.

(1)

Subject to the provisions of this Order and to the requirements, the undertaker is granted—

(a)

development consent for the authorised development; and

(b)

consent for the ancillary works,

to be carried out within the Order limits.

(2)

Work Nos. 1 to 4B must be constructed within the Order limits seaward of MHWS and Work Nos. 4C to 14 must be constructed within the Order limits landward of MHWS.