# The North Falls Offshore Wind Farm Order 2026, Paragraph 12: Ecological management plan


(1) No stage of the onshore works may commence until for that stage an ecological management plan in accordance with the outline landscape and ecological management strategy as appropriate for the relevant stage, has been submitted to and approved by the discharging authority in consultation with the relevant SNCB and the Environment Agency.
(2) The ecological management plan(s) submitted under sub-paragraph (1) must include an implementation timetable and must be implemented as approved.
(3) Onshore site preparation works must only take place in accordance with the relevant details set out in the outline landscape and ecology management strategy as certified in accordance with article 41 (certification of plans and documents, etc).

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/12 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.