OpenLegislation

Paragraph 13 Soil management plan

Original text. Later amendments are not shown.

(1)

No stage of the onshore works may commence until for that stage a soil management plan in accordance with the measures set out in the code of construction practice as appropriate for the relevant stage, has been submitted to and approved by the discharging authority in consultation with the relevant SNCB.

(2)

The onshore works must be carried out in accordance with the approved soil management plan(s).