# The North Falls Offshore Wind Farm Order 2026, Paragraph 19: Onshore build options


(1) Subject to sub-paragraph (2), the undertaker may commence onshore works or exercise powers of compulsory acquisition under Part 5 of this Order, in relation to only either—
(a) build option 1; or
(b) build option 2.
(2) Other than Work No. 9, the onshore works must not commence, nor powers of compulsory acquisition under Part 5 of this Order be exercised, until notification has been submitted to the discharging authority as to whether the undertaker intends to commence build option 1 or build option 2. The undertaker may commence or exercise powers of compulsory acquisition under Part 5 of this Order in relation only to either build option 1 or build option 2.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/19 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.