{
  "url": "https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-21",
  "json_url": "https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-21.json",
  "legislation": "uksi/2026/567",
  "legislation_title": "The North Falls Offshore Wind Farm Order 2026",
  "legislation_url": "https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026",
  "path": "schedule/1/paragraph/21",
  "kind": "paragraph",
  "number": "21",
  "heading": "Biodiversity net gain",
  "text": "(1) Work No. 11 and Work No. 12 must not be commenced until a biodiversity net gain assessment report (which must accord with the approach outlined in the biodiversity net gain strategy) in relation to that stage has been submitted to and approved by the discharging authority in consultation with the relevant SNCB.\n(2)",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/21",
    "retrieved_at": "2026-10-28T21:00:48.162639+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}