# The North Falls Offshore Wind Farm Order 2026, Paragraph 22: The biodiversity net gain assessment report must be implemented as approved. Operational Drainage Strategy


(1) No part of Work No. 11 or Work No. 12 may commence until an operational drainage strategy for operation of that part has been submitted to and approved by the discharging authority in consultation with the Environment Agency.
(2) The operational drainage strategy must be in accordance with the outline operational drainage strategy.
(3) The operational drainage strategy must be implemented as approved.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/22 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-22
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.