Paragraph 4 Stages of authorised development onshore
(1)
The onshore works must not be commenced until notification has been submitted to the discharging authority detailing whether the onshore works will be constructed—
(a)
in a single stage; or
(b)
in two or more stages.
(2)
The onshore works may not be commenced until written details of the stages of the onshore works have been submitted to the discharging authority.
(3)
The construction of the onshore works must follow the written details provided under sub-paragraph (2) of this requirement.