# The North Falls Offshore Wind Farm Order 2026, Paragraph 6: Detailed design parameters onshore


(1) The onshore works must not exceed the parameters set out in the following table and sub-paragraph (2)—
(1)
Parameter
(2)
Value
Maximum number of landfall transition joint bays
2
(2) In relation to Work No. 11 (onshore substation)—
(a) the highest part of any building, any external electrical equipment or enclosure, excluding lightning rods, must not exceed a height of 13m above Ordnance Datum;
(b) the total area of the fenced compound (excluding its accesses) must not exceed 58,800m2; and
(c) the lightning rods within the fenced compound must not exceed a height of 18m above Ordnance Datum.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/6 (the official version)