# The North Falls Offshore Wind Farm Order 2026, Paragraph 7: Provision of landscaping


(1) Work No. 11 must not commence until a written landscaping scheme and associated work programme in accordance with the outline landscape and ecological management strategy for Work No. 11 has been submitted to and approved by the discharging authority in consultation with the relevant SNCB.
(2) The written landscaping scheme must include details of all proposed hard and soft landscaping works including—
(a) location, number, species, size and planting density of any proposed planting including any trees; and
(b) implementation timetables for all landscaping works within Work No. 11.
(3) The landscaping must be carried out in accordance with the approved written landscaping scheme.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/1/paragraph/7 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-1/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.