Paragraph 8 Code of construction practice
(1)
No stage of the onshore works may commence until a code of construction practice (which must accord with the outline code of construction practice) for that stage has been submitted to and approved by the discharging authority in consultation with the relevant SNCB and the Environment Agency.
(2)
The onshore works must be constructed in accordance with the approved code of construction practice.