# The North Falls Offshore Wind Farm Order 2026, Paragraph 9: Construction traffic management plan


(1) No stage of the onshore works may commence until for that stage a construction traffic management plan (which must accord with the outline construction traffic management plan) for that stage has been submitted to and approved by the discharging authority in consultation with National Highways.
(2) The onshore works must be carried out in accordance with the approved construction traffic management plan.

---