# The North Falls Offshore Wind Farm Order 2026, Paragraph 149: Compulsory acquisition of land and rights


In so far as National Grid has acquired an interest in plots 16-006, 16-007 and 16-008 and/or is in occupation of any part of those plots, the undertaker may not exercise temporary possession powers over plots 16-006, 16-007 and 16-008 without the prior agreement of National Grid to such exercise being obtained, which consent must not be unreasonably withheld or delayed.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/149 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-14/paragraph-149
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.