# The North Falls Offshore Wind Farm Order 2026, Paragraph 152: Works in the EACN Substation Area


At all times after National Grid has commenced construction and when the undertaker is—
(a) working within plots 16-006, 16-007 and 16-008; and
(b) within any area within the ownership or control of National Grid; and/or
(c) are carrying out any Specified Works; but
(d) (excepting any works which are works regulated by the connection agreement between the undertaker and National Grid Energy Systems Operator (or a successor thereto) and carried out within the New National Grid Substation Boundary which will be governed solely by that agreement and not this Part;
to comply with paragraphs 153 and 154 of this Part.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/152 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-14/paragraph-152
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.