# The North Falls Offshore Wind Farm Order 2026, Paragraph 183: Access


If in consequence of the exercise of the powers conferred by this Order the access to any apparatus is materially obstructed the undertaker must provide such alternative means of access to that apparatus as will enable EPN to maintain or use the apparatus no less effectively than was possible before the obstruction.

---
Source: https://www.legislation.gov.uk/uksi/2026/567/schedule/14/paragraph/183 (the official version)
Page: https://openlegislation.uk/north-falls-offshore-wind-farm-order-2026/schedule-14/paragraph-183
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.